It is the question we are asked most often – more often than any question about material, mesh size or pressure rating: How long will it take? It is usually in the very first message, even before the price.
An honest answer is: it depends on what you order. But that does not help anyone. So here is what actually determines the delivery time – and how you can tell in advance whether your strainer will arrive in weeks or in months.
At a glance
Catalogue goods
Short and predictable
Witch hat and flat plate strainers, line blinds and strainer gaskets are standardised – the dimensions are fixed.
Engineered design
Several fixed steps
Basket, duplex and T-type strainers are built to your operating conditions. The steps cannot be skipped.
Spare parts
Almost always fast
A replacement screen made to size or to sample needs neither a design proposal nor an inspection.
Catalogue goods and engineered designs are two different worlds
The biggest difference lies in whether a part comes from the catalogue or is designed for your plant.
Catalogue goods
Witch hat strainers, flat plate strainers, line blinds and strainer gaskets are standardised. You select the nominal size, pressure rating and mesh size; the dimensions are fixed. Here, the delivery time is short and predictable.
Engineered design
A basket strainer, duplex strainer or T-type strainer, on the other hand, is not a stock item. Every unit is made for a specific operating situation: medium, pressure, temperature, installation position, required certificates. Between order and dispatch there are several steps that cannot be skipped.
What happens between order and delivery
Design and approval drawing
We calculate the wall thicknesses according to the code, define connections and face-to-face lengths and send you a drawing. Until you approve it, manufacturing is on hold – this is the step that is most often underestimated.
Material procurement
Plates and flanges in the right grade must be available. For 1.4571 in common thicknesses this is quick; for special alloys or large wall thicknesses it can take weeks.
Manufacturing
Cutting, welding, strainer basket, add-on parts. This is the part people imagine as “build time” – and often not the longest one.
Surface treatment
Pickling and passivation for stainless steel, priming and painting for carbon steel. Both need time to dry and are partly carried out externally.
Testing and documentation
Pressure test with report, certificates, operating instructions, declaration of conformity.
Three things that noticeably extend it
A TÜV inspection
It takes place on the open unit while it can still be inspected and must be scheduled with the inspection body. This is not a matter of hours but of the next available appointment. If you need an inspection, say so in the enquiry – not only when you place the order.
An inspection certificate 3.1
It links a specific component to the heat from which it originates. This requires the material to pass through manufacturing together with its certificate from the very beginning. A 3.1 certificate cannot be issued retrospectively – if it is requested later, procurement starts again from scratch.
Special alloys and large nominal sizes
From DN500 upwards, plates and flanges are no longer stock items. The same applies to materials beyond the usual stainless steels. Here, procurement determines the date, not the workshop.
What you can do to speed things up
- Send a complete enquiry. Medium, pressure, temperature, nominal size, mesh size, required certificates. Every missing detail costs a query – and the clock is not running with us but between two inboxes.
- Name certificates and inspection early. Both must be settled before manufacturing, not afterwards.
- Approve the drawing promptly. Between dispatch and approval, manufacturing stands still.
- Ask whether it has to be a custom design. Sometimes a catalogue item will do – a witch hat strainer instead of a strainer housing, for example, if only the start-up phase needs to be protected.
When it is urgent
Say so straight away in the enquiry. Not every order can be accelerated – an inspection remains an inspection. But much can be arranged differently: ordering material early, agreeing the drawing in advance, arranging a partial delivery if only part of the plant is waiting.
Spare parts are almost always quick. A replacement screen made to size or to sample needs neither design nor inspection. Outside diameter, height, mesh size and material are enough – or a photo of the old part.
A reliable delivery date
Tell us what is to be filtered and by when it must be in place. We will tell you what is possible – and what is not.